Conduit and handhole placements along Lindale Drive and Lindale Circle have been completed. About half of the teal shaded area along Hutchins Lane has been completed and should be completed this week.
Pending permits with TXDOT to cross West Loop have been approved and that crossing will happen later this week. After this week, crews will move into the Myatt Lane area and fiber will begin to be pulled through the conduit for splicing to start.
The first group of customers to be connected could happen as early as October.