Construction for all of Zone A is complete, with the exception of the Regency neighborhood. The Regency construction will begin this week.
Equipment shells have been installed on the homes with pending orders for service. Splicing and additional testing will continue this and next week.
The sales department is current calling to begin scheduling orders and the first set of installs should be happening the week of October 21 - 25.