Crews have been working along Appling Street the past couple of days and we should have the initial phase of construction completed for Area 2 of Zone C by the end of next week.
Area 1 of Zone C is having splicing work finished and clamshell enclosures mounted on the exterior of homes next week. Crew members will always attempt to notify homeowners before entering the property and gain access to gates.
Customers in Area 1 could see services installed and turned up for service the week of May 5th.