Construction work for the distribution plant serving Zone E Group 2 will be nearing completion by the end of this week. This includes the placement of drops to residences that had placed orders before construction began. Splicing for this area will begin this week as well.
We look to be construction complete with Group 2 next week at which time we will roll into Zone E Group 1. Splicing for Group 2 will continue as the construction work for Group 1 begins. Increased contactor activity in the area should be expected.