Our Construction Contractor has been busy placing duct for Zone G. We started off at a rapid pace with few interruptions until the February ice storm set in.
Now that weather has improved, contractors have made significant progress over the past week. Duct has been placed for our feeder cable beginning at our launch point near the intersection of Church St. and Ave. A, all the way to our proposed splitter cabinet location near the intersection of Erin St. and Ave, D.
Construction on the distribution plant began March 11. Contractors will continue placing duct in the distribution plant for the next 2-3 weeks. Due to a material shipment delay, we will be monitoring timelines and making any necessary adjustments in the upcoming week.